    NEVI and public chargers: how the US federal charging program works

    The National Electric Vehicle Infrastructure (NEVI) Formula Program, created by the 2021 infrastructure law, gives states $5 billion to build EV chargers, first along designated highway corridors.[1] Federal rules require funded stations to have at least four fast-charging ports, deliver up to 150 kW per port and stay up more than 97% of the time.[2][3] After the Federal Highway Administration withheld funds in 2025, a federal judge ordered them restored to 14 of the suing states, and FHWA issued revised guidance in August 2025.[4][5]

    Editor reviewedUpdated Explainer12 claims · 100% primaryElectric and self-driving vehicles, Transport, Tech policy
    Reading level: 4 passages differ; the rest is the same for everyone.

    This explainer covers the federal NEVI Formula Program and the federal standards for publicly funded chargers. It does not track individual state plans or station openings, and court cases can change (we have not tracked any appeal); check FHWA and your state transportation agency for current status. How charging itself works is in EV charging explained.

    What NEVI is

    NEVI is a federal program that gives states $5 billion to build public chargers for electric vehicles. Congress created it in the 2021 Infrastructure Investment and Jobs Act. The money goes first to chargers along major highway routes that the government has designated as charging corridors.[1]

    The Infrastructure Investment and Jobs Act (Public Law 117-58) established the NEVI Formula Program, which provides $5 billion to states for EV charging infrastructure, initially directed to designated Alternative Fuel Corridors (AFCs).[1] States prepare deployment plans that FHWA approves, and the federal minimum standards in 23 CFR Part 680 apply to NEVI projects and to publicly accessible chargers funded under Title 23.[6][7]

    The federal standards

    Stations paid for by the program have to meet national rules. Along highway corridors, each station needs at least four fast-charging plugs that can charge four cars at the same time, each able to deliver up to 150 kW.[2] Each charger must work more than 97% of the time over a year.[3] Equipment must be safety-certified by an approved testing laboratory.[8]

    23 CFR 680.106 requires corridor stations to have at least four network-connected DC fast-charging ports capable of simultaneously charging four EVs, each supplying up to 150 kW on request.[2] Section 680.116 requires average annual uptime above 97% per port.[3] Chargers must be certified by an OSHA Nationally Recognized Testing Laboratory, and Level 2 units must be ENERGY STAR certified.[8] The rule requires CCS connectors on fast-charging ports and J1772 on Level 2 ports; the debate over the SAE J3400 plug is covered in NACS charging standard explained.[9]

    The 2025 funding freeze and the courts

    In February 2025, the Federal Highway Administration told states it was cancelling earlier approvals of their charging plans and holding back the money, according to Washington’s attorney general, a party to the case. It says sixteen states and Washington, D.C. sued in May 2025.[7] In June 2025 a federal judge in Washington state ordered the money restored for 14 of those states.[4] In a final ruling announced in January 2026, the judge barred the government from withholding the suing states’ funds for reasons Congress had not authorised, the Washington attorney general said.[10]

    Washington’s attorney general says FHWA notified states in February 2025 that it was revoking prior state plan approvals and withholding NEVI funds, and that a coalition of 16 states and the District of Columbia sued on 7 May 2025.[7] US District Judge Tana Lin issued a preliminary injunction in June 2025 requiring the restoration of the plaintiff states’ deployment plans and an end to withholding their funds; NPR reported it covered 14 states.[4] On summary judgment, announced on 26 January 2026, she found the agencies’ actions outside the law and arbitrary and capricious, and barred future suspension or revocation of the plaintiffs’ approved plans, according to the Washington attorney general.[10]

    The August 2025 guidance

    In August 2025 the agency issued new program guidance. It says the changes give states more flexibility. States now decide how far apart corridor stations should be, and no longer have to plan for consumer protections, emergency evacuations, environmental siting, resilience or terrain.[5][11]

    FHWA’s interim final guidance took effect on 13 August 2025. FHWA describes it as streamlining the program and giving states flexibility, in line with Executive Order 14154.[5] It rescinds earlier guidance and policy not required by clear and express statutory language, and revises the 11 June 2024 guidance.[12] States now set station spacing along corridors, and requirements to address consumer protections, emergency evacuation plans, environmental siting, resilience and terrain were removed.[11] As of November 2026, the minimum standards in 23 CFR Part 680, including the four-port, 150 kW and 97% uptime rules, remain in the eCFR text.[2][3]

    More in EVs & robotaxis

    Developing in Science & Energy

    Questions readers ask

    What is the NEVI program?

    A $5 billion federal formula program, created by the 2021 Infrastructure Investment and Jobs Act, that funds states to deploy EV charging, initially along designated Alternative Fuel Corridors.[1]

    What must a NEVI-funded charging station provide?

    Corridor stations need at least four networked DC fast-charging ports that can charge four EVs at once at up to 150 kW each, and each port must average more than 97% uptime a year.[2][3]

    Was NEVI funding frozen?

    Washington's attorney general says FHWA told states in February 2025 it was revoking plan approvals and withholding funds. A federal judge ordered the funds restored to 14 suing states in June 2025.[7][4]

    What changed in the August 2025 guidance?

    FHWA's revised guidance lets states decide the distance between corridor stations and dropped requirements to address consumer protections, evacuation plans, environmental siting, resilience and terrain.[11]

    Sources

    · 12 claims from 4 publishers

    Each numbered claim is a statement we checked against the sources listed with it. Tap a number in the text to see its sources in place.

    1. [1]

      The NEVI Formula Program, created by the 2021 Infrastructure Investment and Jobs Act, provides $5 billion to states for EV charging, initially directed to designated Alternative Fuel Corridors. confirmedas of 2025-08-13

    2. [2]

      Under 23 CFR 680.106, corridor charging stations must have at least four networked DC fast-charging ports able to charge four vehicles at once, and each port must be able to deliver up to 150 kW simultaneously. confirmedas of 2026-11-21

    3. [3]

      The federal rules require each charging port to have an average annual uptime above 97%. confirmedas of 2026-11-21

    4. [4]

      In June 2025 US District Judge Tana Lin ordered the administration to restore the plaintiff states' EV infrastructure deployment plans and stop withholding their NEVI funds, a preliminary injunction covering 14 states. confirmedas of 2025-06-25

    5. [5]

      The Federal Highway Administration issued revised NEVI interim final guidance effective 13 August 2025, which it said streamlines the program and gives states more flexibility, in line with Executive Order 14154. confirmedas of 2025-08-13

    6. [6]

      23 CFR Part 680 sets minimum standards for NEVI Formula Program projects and for publicly accessible EV chargers built with federal highway funds under Title 23. confirmedas of 2026-11-21

    7. [7]

      According to Washington's attorney general, the Federal Highway Administration told states in February 2025 that it was revoking earlier approvals of state NEVI plans and withholding program funds; 16 states and the District of Columbia sued on 7 May 2025. reportedas of 2025-06-24

    8. [8]

      Chargers funded under the rules must be certified by an OSHA Nationally Recognized Testing Laboratory, and Level 2 chargers must be ENERGY STAR certified. confirmedas of 2026-11-21

    9. [9]

      The current eCFR text of 23 CFR 680.106 requires each DC fast-charging port to have at least one permanently attached CCS Type 1 connector and each AC Level 2 port a permanently attached J1772 connector. confirmedas of 2026-11-21

    10. [10]

      In a final ruling announced on 26 January 2026, Judge Lin found the Transportation Department and FHWA acted outside the law and arbitrarily, and barred them from suspending or revoking the plaintiff states' approved plans or withholding their NEVI funds for reasons Congress has not expressly authorised, according to Washington's attorney general. reportedas of 2026-01-26

    11. [11]

      Under the August 2025 guidance, states decide the distance between stations along corridors and no longer have to address consumer protections, emergency evacuation plans, environmental siting, resilience and terrain. confirmedas of 2025-08-13

    12. [12]

      FHWA said its August 2025 guidance rescinds earlier guidance and policy not required by clear and express statutory language, and changes the guidance document dated 11 June 2024. confirmedas of 2025-08-13

    Revision history (1)
    1. Page created.

    Created Nov 21, 2026. Last reviewed by an editor on Nov 22, 2026. Next scheduled review: May 24, 2027.