    DOE emergency orders keeping coal plants open: section 202(c)

    Section 202(c) of the Federal Power Act lets the federal government order electricity generation or transmission to meet an emergency; orders that may conflict with environmental law last up to 90 days and can be renewed.[1] Since May 2025 DOE has used it to keep coal plants that were due to retire available, starting with J.H. Campbell in Michigan, and later Craig Unit 1 in Colorado and Centralia Unit 2 in Washington.[2][3][4] On 11 September 2026 the D.C. Circuit vacated the first Campbell order, holding that DOE exceeded its authority.[5] DOE has since issued a further Campbell order running from 15 November 2026 to 12 February 2027.[6]

    Editor reviewedUpdated Explainer16 claims · 69% primaryEnergy and climate

    The US Department of Energy (DOE) has used an emergency power in the Federal Power Act, section 202(c), to keep coal plants that were due to retire available to run.[2][3] This page explains what the law allows, which plants have been ordered to stay open, the arguments on each side and the September 2026 court ruling. For how coal power works, see coal power explained.

    This page reports orders and court rulings as of 14 November 2026. It attributes the positions of DOE, states and other parties to them and does not take a side.

    What section 202(c) allows

    Section 202(c) allows emergency orders during a war, or when an emergency exists because of a sudden increase in demand for electricity, or a shortage of electricity, of generating or transmission facilities, or of fuel or water. An order that may conflict with environmental law expires after no more than 90 days, but it can be renewed for further periods of up to 90 days each.[1] A September 2026 summary by the law firm Willkie Farr & Gallagher notes that the Secretary of Energy exercises this authority and that, unlike section 202(b), it does not need an application from a state commission or utility.[7]

    The J.H. Campbell orders

    On 23 May 2025 DOE issued Order No. 202-25-3, directing the grid operator MISO, in coordination with Consumers Energy, to keep the J.H. Campbell coal plant in West Olive, Michigan available to operate. The plant had been due to shut on 31 May 2025.[2] In June 2025 the Michigan Attorney General, Minnesota and Illinois, the Organization of MISO States and a group of public interest organisations asked DOE to rehear the order.[8]

    DOE renewed the order five times. The six orders together required about 450 days of operation, and the sixth ran until 14 November 2026.[9] DOE then issued another order keeping the plant available from 15 November 2026 through 12 February 2027. DOE said events during the winter 2026 Arctic cold period, including Winter Storm Fern, showed the need for dispatchable generation such as Campbell.[6]

    Craig, Centralia and other plants

    Craig Unit 1 in Colorado was due to close at the end of 2025. DOE’s orders for it include those issued in December 2025, March 2026 and on 26 June 2026; the June order, in effect from 29 June to 26 September 2026, directed the grid operator SPP to use economic dispatch to keep costs down.[3] On 24 July 2026 the State of Colorado, public interest groups and two of Craig’s co-owners, Tri-State Generation and Transmission Association and Platte River Power Authority, asked for rehearing.[10]

    DOE also ordered TransAlta to keep Unit 2 of the Centralia coal plant in Washington state, which had been due to shut at the end of 2025, available from 13 September to 11 December 2026.[4] Willkie Farr & Gallagher wrote in September 2026 that similar orders had been issued to at least six other coal-fired generators across the country.[11]

    Arguments for and against

    DOE says keeping plants such as Campbell available has prevented blackouts and likely saved lives, and that more than 17 GW of coal-fired generation was saved from going offline in 2025.[12]

    The Michigan Attorney General’s office argues that the Campbell order disregarded earlier planning and regulatory approvals. It also said Consumers Energy reported $295 million in costs for the plant from May 2025 to 30 June 2026, which the utility is seeking to recover from customers across MISO’s north and central regions.[13] A September 2026 Willkie Farr & Gallagher summary gave a different figure, citing Consumers Energy: $259 million for complying with the order.[14]

    The September 2026 court ruling

    On 11 September 2026 a unanimous three-judge panel of the US Court of Appeals for the D.C. Circuit vacated DOE’s first Campbell order, holding that DOE had exceeded its authority under section 202(c), in Michigan v. Department of Energy (No. 25-1159).[5] According to Willkie Farr & Gallagher’s summary, the court read section 202(c) as a last-resort tool for emergencies, noted that the NERC report DOE cited found MISO had adequate anticipated resources, and said the repeated renewals showed the situation was not a transitory emergency.[15]

    The same summary said challenges to the later Campbell orders, held in abeyance, would now proceed; that a FERC case on whether Consumers Energy can pass the costs on to ratepayers remained pending; and that DOE could ask the full D.C. Circuit to rehear the case.[16]

    US Department of Energy (DOE)

    The US Department of Energy runs 17 national labs, the nuclear weapons stockpile, energy loans and the Genesis AI mission. Its role and FY 2027 budget.

    More in Energy and climate

    Developing in Science & Energy

    Go deeper

    Questions readers ask

    What is a section 202(c) order?

    Section 202(c) of the Federal Power Act allows emergency orders during a war, or when an emergency exists because of a sudden increase in demand or a shortage of electricity, generating or transmission facilities, or fuel or water. An order that may conflict with environmental law expires after no more than 90 days but can be renewed for further 90-day periods. A September 2026 law firm summary notes that the Secretary of Energy exercises the power and that it does not require an application from a state or utility.[1][7]

    Which coal plants has DOE ordered to stay open?

    DOE pages confirm orders for J.H. Campbell in Michigan (from May 2025), Craig Unit 1 in Colorado (from December 2025) and Centralia Unit 2 in Washington (an order running from September to December 2026). A law firm summary said in September 2026 that similar orders had gone to at least six other coal-fired generators besides Campbell.[2][3][4][11]

    What did the court decide about the Campbell plant?

    On 11 September 2026 a unanimous D.C. Circuit panel vacated DOE's first Campbell order, holding that DOE had exceeded its authority under section 202(c). The case is Michigan v. Department of Energy, No. 25-1159.[5]

    Is the Campbell plant still running?

    DOE has kept issuing orders. After the six orders that ran until 14 November 2026, it issued another keeping the plant available from 15 November 2026 to 12 February 2027.[9][6]

    Why does DOE say the orders are needed?

    DOE says keeping plants such as Campbell available has prevented blackouts and likely saved lives, and that more than 17 GW of coal-fired generation was saved from going offline in 2025.[12]

    Who is challenging the orders?

    Michigan, Minnesota and Illinois, the Organization of MISO States and public interest groups sought rehearing of the first Campbell order. For Craig, the State of Colorado, public interest groups and two of the plant's co-owners filed rehearing requests in July 2026.[8][10]

    Sources

    · 16 claims from 5 publishers

    Each numbered claim is a statement we checked against the sources listed with it. Tap a number in the text to see its sources in place.

    1. [1]

      Section 202(c) of the Federal Power Act allows orders requiring electricity generation, delivery or transmission during a war or when an emergency exists because of a sudden increase in demand, or a shortage of electricity, generating or transmission facilities, or fuel or water; an order that may conflict with environmental law expires after no more than 90 days but can be renewed for further 90-day periods. confirmedas of 2026-11-14

    2. [2]

      On 23 May 2025 DOE issued Order No. 202-25-3 under section 202(c), directing the grid operator MISO, in coordination with Consumers Energy, to keep the J.H. Campbell coal plant in West Olive, Michigan available to operate; the plant had been due to shut on 31 May 2025. confirmedas of 2026-11-14

    3. [3]

      Craig Unit 1, a coal unit in Colorado, was due to close at the end of 2025; DOE has kept it available under emergency orders issued in December 2025, March 2026 and on 26 June 2026, the last in effect from 29 June through 26 September 2026, directing the grid operator SPP to use economic dispatch to minimise costs. confirmedas of 2026-11-14

    4. [4]

      DOE ordered TransAlta to keep Unit 2 of the Centralia coal plant in Washington state, which had been scheduled to shut at the end of 2025, available to operate from 13 September through 11 December 2026. confirmedas of 2026-11-14

    5. [5]

      On 11 September 2026 a three-judge panel of the US Court of Appeals for the D.C. Circuit unanimously vacated DOE's first Campbell order, holding that DOE had exceeded its authority under section 202(c), in Michigan v. Department of Energy (No. 25-1159). confirmedas of 2026-09-17

    6. [6]

      DOE issued a further emergency order keeping the Campbell plant available to operate from 15 November 2026 through 12 February 2027, citing lessons from the winter 2026 Arctic cold period, including Winter Storm Fern. confirmedas of 2026-11-14

    7. [7]

      The authority in section 202(c) is exercised by the Secretary of Energy, and it can be used without an application from a state or utility, unlike section 202(b), according to a September 2026 Willkie Farr & Gallagher summary of the D.C. Circuit's Campbell ruling. reportedas of 2026-09-17

    8. [8]

      In June 2025 the Michigan Attorney General, the states of Minnesota and Illinois, the Organization of MISO States and a group of public interest organisations asked DOE to rehear the first Campbell order; DOE issued an order addressing the rehearing arguments on 8 September 2025. confirmedas of 2026-11-14

    9. [9]

      DOE renewed the Campbell order five times, issuing six successive orders that together required about 450 days of operation; the sixth ran until 14 November 2026. confirmedas of 2026-09-17

    10. [10]

      On 24 July 2026 the State of Colorado, a group of public interest organisations and two of Craig's co-owners, Tri-State Generation and Transmission Association and Platte River Power Authority, filed requests for rehearing of the June 2026 Craig order. confirmedas of 2026-11-14

    11. [11]

      Willkie Farr & Gallagher wrote in September 2026 that similar DOE orders had been issued to at least six other coal-fired generators across the country. reportedas of 2026-09-17

    12. [12]

      DOE says keeping plants such as Campbell available has prevented blackouts and likely saved lives, and that more than 17 GW of coal-fired generation was saved from going offline in 2025. confirmedas of 2026-11-14

    13. [13]

      The Michigan Attorney General's office argues that the Campbell order disregarded prior planning and regulatory approvals, and said Consumers Energy reported $295 million in costs for the plant from May 2025 to 30 June 2026, which it is seeking to recover from customers across MISO's north and central regions. reportedas of 2026-09-11

    14. [14]

      Willkie Farr & Gallagher's September 2026 summary put the cost of complying with the Campbell emergency order at $259 million, citing Consumers Energy. reportedas of 2026-09-17

    15. [15]

      According to Willkie Farr & Gallagher's summary, the court read section 202(c) as a last-resort tool for imminent emergencies; it noted that the NERC report DOE cited found MISO had adequate anticipated resources, and said the roughly 450 days of renewals showed the situation was not a transitory emergency. reportedas of 2026-09-17· interpretation

    16. [16]

      Willkie Farr & Gallagher wrote that the separate challenges to the Campbell renewal orders, which had been held in abeyance, would now proceed, that a FERC proceeding on whether Consumers Energy can pass the costs on to ratepayers remained pending, and that DOE could seek rehearing by the full D.C. Circuit. reportedas of 2026-09-17

    Revision history (1)
    1. Page created.

    Created Nov 14, 2026. Last reviewed by an editor on Nov 15, 2026. Next scheduled review: Feb 12, 2027.