    DOE's Reactor Pilot Program explained

    The Reactor Pilot Program is a Department of Energy pathway for authorizing and testing advanced reactor designs, created after a May 2025 executive order set a goal of three reactors reaching criticality by 4 July 2026.[1][2] DOE picked 11 projects from 10 companies in August 2025.[3] Between 4 June and 4 July 2026, DOE announced that four DOE-authorized advanced reactors had reached criticality: Antares Nuclear's Mark-0, Valar Atomics' Ward 250, Deployable Energy's Unity and Aalo Atomics' Aalo-X.[4][5][6][7]

    Editor reviewedUpdated Explainer18 claims · 100% primaryEnergy and climate
    Reading level: 1 passage differs; the rest is the same for everyone.

    A May 2025 executive order found that advanced reactors under sufficient Department of Energy control that do not produce commercial electric power fall within DOE’s jurisdiction. Companies in the Reactor Pilot Program seek DOE authorization under the Atomic Energy Act to test their designs.[8] The program grew out of one of four nuclear executive orders signed on 23 May 2025.[9]

    Where the program came from

    Executive Order 14301 directed DOE to create a pilot program for reactor construction and operation outside the national laboratories. DOE was to approve at least three reactors, with the goal of each reaching criticality by 4 July 2026.[2]

    DOE issued its request for applications on 18 June 2025. Initial applications closed on 21 July 2025, and later applications were accepted on a rolling basis.[10] DOE describes the result as a new DOE pathway for advanced reactor demonstration, meant to fast-track commercial licensing.[1]

    A reactor is critical when each fission releases enough neutrons to keep an ongoing series of reactions going.[11]

    The selected projects

    On 12 August 2025 DOE announced 11 initial projects from 10 companies: Aalo Atomics, Antares Nuclear, Atomic Alchemy, Deep Fission, Last Energy, Oklo (two projects), Natura Resources, Radiant Industries, Terrestrial Energy and Valar Atomics.[3] DOE said each company would pay all costs of designing, building, operating and decommissioning its test reactor.[12]

    DOE set the program’s goal as criticality for at least three advanced reactor concepts located outside the national laboratories.[13] DOE also says four of the projects were to be hosted at the Idaho National Laboratory site: Radiant’s KDU, Antares’s Mark-0, Aalo-X and Oklo’s Aurora.[14]

    On 5 March 2026 DOE and the National Reactor Innovation Center set up the Nuclear Energy Launch Pad, which DOE calls the next evolution of the Reactor Pilot Program.[15]

    The four criticality tests in 2026

    DateReactorDeveloperSiteRoute
    4 June 2026Mark-0Antares NuclearIdaho National LaboratoryReactor Pilot Program[4]
    18 June 2026Ward 250Valar AtomicsUtah San Rafael Energy Lab, Emery CountyReactor Pilot Program[5]
    30 June 2026UnityDeployable EnergyIdaho National LaboratoryNuclear Energy Launch Pad[6]
    4 July 2026Aalo-XAalo AtomicsIdaho National LaboratoryReactor Pilot Program[7]

    DOE called the Mark-0 test the first time in over 40 years that a new privately developed non-light-water reactor had reached criticality in the US.[4] It said that zero-power fueled demonstration set a baseline for later reactors to produce electricity in 2027 and after.[16]

    Unity was carried out under the Nuclear Energy Launch Pad, managed by the National Reactor Innovation Center at Idaho National Laboratory. DOE counted it as the third DOE-authorized advanced reactor to go critical by the deadline.[6] Aalo-X followed on 4 July as the fourth.[7] DOE says it met and exceeded the executive order’s goal.[17]

    What comes next

    DOE has said the first test set a baseline for later reactors to produce electricity in 2027 and the years after.[16] The program page says applications after the initial July 2025 round are allowed on a rolling basis.[10] For the wider set of goals in the May 2025 orders, including the 400 GW target and NRC reform, see our explainer on the nuclear executive orders.[18]

    This page relies mainly on DOE’s own announcements. It does not cover NRC licensing of these designs for commercial use, which is a separate process.

    US Department of Energy (DOE)

    The US Department of Energy runs 17 national labs, the nuclear weapons stockpile, energy loans and the Genesis AI mission. Its role and FY 2027 budget.

    More in Energy and climate

    Developing in Science & Energy

    Go deeper

    Questions readers ask

    What is the Reactor Pilot Program?

    A DOE pathway for demonstrating advanced reactors under DOE authorization, which DOE says is meant to fast-track later commercial licensing.[1]

    Why was it set up?

    Executive Order 14301 of May 2025 told DOE to create a pilot program for reactors outside the national laboratories and approve at least three, with the goal of each reaching criticality by 4 July 2026.[2]

    Which companies were selected?

    In August 2025 DOE named 11 projects from Aalo Atomics, Antares Nuclear, Atomic Alchemy, Deep Fission, Last Energy, Oklo (two projects), Natura Resources, Radiant Industries, Terrestrial Energy and Valar Atomics.[3]

    Did the program meet its goal?

    DOE says it exceeded it. Four DOE-authorized advanced reactors reached criticality between 4 June and 4 July 2026.[17][4][7]

    Who pays for the reactors?

    DOE said each selected company is responsible for all costs of designing, building, operating and decommissioning its test reactor.[12]

    Do these reactors make electricity?

    DOE described the first test as a zero-power fueled criticality demonstration that set a baseline for later reactors to produce electricity in 2027 and after.[16]

    Sources

    · 18 claims from 4 publishers

    Each numbered claim is a statement we checked against the sources listed with it. Tap a number in the text to see its sources in place.

    1. [1]

      DOE describes the programme as a new DOE authorization pathway for demonstrating advanced reactors that is meant to fast-track later commercial licensing. confirmedas of 2026-08-10

    2. [2]

      Executive Order 14301 directs DOE to create a pilot program for reactors outside the national laboratories and to approve at least three, with the goal of each reaching criticality by 4 July 2026. confirmedas of 2025-05-29

    3. [3]

      On 12 August 2025 DOE announced 11 initial projects from 10 companies, Aalo Atomics, Antares Nuclear, Atomic Alchemy, Deep Fission, Last Energy, Oklo (two projects), Natura Resources, Radiant Industries, Terrestrial Energy and Valar Atomics. confirmedas of 2025-08-12

    4. [4]

      On 4 June 2026 DOE announced that Antares Nuclear's Mark-0 reactor had reached criticality in a test at Idaho National Laboratory, which DOE called the first time in over 40 years that a new privately developed non-light-water reactor reached criticality in the US. confirmedas of 2026-07-25

    5. [5]

      On 18 June 2026 DOE announced that Valar Atomics' Ward 250 test reactor had reached criticality at the Utah San Rafael Energy Lab in Emery County, Utah. confirmedas of 2026-07-25

    6. [6]

      On 30 June 2026 Deployable Energy's Unity reactor reached criticality at Idaho National Laboratory under the Nuclear Energy Launch Pad, managed by the National Reactor Innovation Center; DOE called it the third DOE-authorized advanced reactor to go critical by the 4 July deadline. confirmedas of 2026-07-01

    7. [7]

      On 4 July 2026 Aalo Atomics' Aalo-X completed a zero-power fueled criticality demonstration at Idaho National Laboratory, the fourth DOE-authorized advanced reactor to reach criticality. confirmedas of 2026-07-06

    8. [8]

      Executive Order 14301 finds that advanced reactors under sufficient DOE control that do not produce commercial electric power fall within DOE's jurisdiction, and DOE says pilot companies seek DOE authorization under the Atomic Energy Act. confirmedas of 2025-08-12

    9. [9]

      On 23 May 2025 the President signed four nuclear energy executive orders, numbered 14299 to 14302, which were published in the Federal Register on 29 May 2025. confirmedas of 2025-05-29

    10. [10]

      DOE issued the Reactor Pilot Program's request for applications on 18 June 2025; initial applications closed on 21 July 2025, with later applications accepted on a rolling basis. confirmedas of 2026-08-10

    11. [11]

      The NRC says a reactor achieves criticality when each fission event releases enough neutrons to sustain an ongoing series of reactions. confirmedas of 2026-11-14

    12. [12]

      DOE said each selected company is responsible for all costs of designing, building, operating and decommissioning its test reactor. confirmedas of 2025-08-12

    13. [13]

      DOE set the programme's goal as criticality for at least three advanced reactor concepts located outside the national laboratories by 4 July 2026. confirmedas of 2026-08-10

    14. [14]

      DOE says four of the pilot projects were to be hosted at the Idaho National Laboratory site, Radiant's KDU, Antares's Mark-0, Aalo-X and Oklo's Aurora. confirmedas of 2026-07-25

    15. [15]

      On 5 March 2026 DOE and the National Reactor Innovation Center set up the Nuclear Energy Launch Pad, which DOE calls the next evolution of the Reactor Pilot Program. confirmedas of 2026-07-25

    16. [16]

      DOE said the Mark-0 test was a zero-power fueled criticality demonstration that set a baseline for later reactors to produce electricity in 2027 and after. confirmedas of 2026-07-25

    17. [17]

      DOE says it met and exceeded the executive order's goal by bringing four advanced reactors to criticality by 4 July 2026. confirmedas of 2026-07-25

    18. [18]

      Executive Order 14300 sets a policy of expanding US nuclear capacity from about 100 GW in 2024 to 400 GW by 2050. confirmedas of 2025-05-29

    Revision history (1)
    1. Page created.

    Created Nov 14, 2026. Last reviewed by an editor on Nov 15, 2026. Next scheduled review: May 14, 2027.