    Small modular reactors explained: designs, promises and costs

    Small modular reactors (SMRs) are fission reactors of generally 300 MWe or less, built from factory-made modules in the hope of cutting cost and construction time.[1] As of November 2026 the leading Western designs had construction permits or licences in Canada and the US, while NuScale's Carbon Free Power Project in Idaho was cancelled in November 2023; its target power price had been raised to $89 per megawatt-hour that January.[2][3][4][5]

    Editor reviewedUpdated Explainer30 claims · 23% primaryEnergy and climate, Physics
    Reading level: 1 passage differs; the rest is the same for everyone.

    A small modular reactor is a fission reactor built smaller and in factory-made pieces. The usual definition is 300 MWe or less, with modules fabricated in factories to gain economies of series production and shorter construction times.[1] The first Western units are only now being licensed and built.[2][6][4]

    This page explains what SMRs are, the main designs and the evidence on cost so far. It assumes the basics in how nuclear fission reactors work. Dated project news is in the SMR projects tracker, and the demand side is covered in the AI data center power tracker.

    What makes a reactor small and modular

    “Small” refers to output. A traditional reactor makes around 1,000 MWe or more, while SMRs are generally 300 MWe or less. The smallest, under about 20 MWe, are sometimes called microreactors.[7][1] “Modular” refers to how they are built. Parts, or even whole reactor modules, are made in factories and shipped to the site for assembly.[8]

    The World Nuclear Association definition is 300 MWe equivalent or less, with module factory fabrication aimed at economies of series rather than economies of scale; some definitions stretch to 600 MWe.[1][7] For a 2025 US funding programme, the DOE defined a Gen III+ SMR more narrowly: light-water-cooled, low-enriched uranium fuel, 50 to 350 MWe per unit.[9] Most near-term candidates use proven water-cooled technology. The other three families are fast neutron, graphite-moderated high-temperature and molten salt reactors.[10]

    The leading designs

    Water-cooled designs lead the field:

    • BWRX-300 (GE Vernova Hitachi): a 300 MWe boiling water reactor with natural circulation and passive safety, derived from the NRC-certified ESBWR.[11]
    • NuScale US460 / VOYGR: 77 MWe modules with core, pressurizer and steam generators in one vessel. The design received NRC standard design approval in May 2025, and plants range from 308 to 924 MWe.[12]
    • Rolls-Royce SMR: a 470 MWe pressurised water reactor, above the usual 300 MWe SMR threshold, with 90% of the reactor unit to be built in factories.[13][1]
    • Linglong One (ACP100): China’s 125 MWe integral PWR with passive decay heat removal, intended for electricity, heat and desalination.[14]

    Non-water designs aim at higher temperatures or different fuel cycles:

    • Natrium (TerraPower): a 345 MWe sodium-cooled fast reactor with molten-salt storage that can boost output to 500 MWe.[15]
    • Xe-100 (X-energy): an 80 MWe high-temperature gas-cooled reactor, planned in four-unit 320 MWe plants.[16]
    • Kairos KP-FHR: a 140 MWe fluoride salt-cooled reactor using TRISO fuel pebbles at up to 650°C, with passive shutdown and decay heat removal.[17] Kairos is first building the Hermes test reactors in Tennessee.[18]

    The claimed benefits

    The US Department of Energy lists small footprints, lower capital investment, siting where large plants cannot go, and the option to add power in increments.[19] It also sees uses beyond electricity, including process heat and desalination.[20] Several designs rely on passive safety, which uses convection and gravity rather than pumps to remove heat.[21][11][14] Natrium pairs its reactor with molten-salt energy storage that can temporarily boost output to 500 MWe when needed.[15]

    Large technology companies have signed deals. In 2024 Google agreed to buy power from multiple Kairos reactors, up to 500 MW by 2035.[22] Amazon invested in X-energy the same month, including manufacturing capacity for more than 5 GW of projects.[23]

    Cost and schedule: the evidence so far

    The clearest data point is NuScale’s Carbon Free Power Project, a planned six-module, 462 MWe plant at Idaho National Laboratory owned by Utah municipal utilities.[24] By January 2023 its target power price had risen to $89 per megawatt-hour. NuScale blamed inflation and higher prices for steel, electrical equipment and other commodities.[5] The project was cancelled in November 2023, before a licence application was filed.[4]

    In Canada, in May 2025 Ontario approved a CAD20.9 billion budget and the start of construction of the first of four planned BWRX-300s, with first grid connection planned by the end of 2030.[25] In the US, Natrium’s construction permit review took 18 months against an initial 27-month schedule, and the Clinch River BWRX-300 review finished four months early.[26][3] TVA had not announced a construction date when its permit was issued.[3] China’s Linglong One completed its steam turbine test in December 2025, but as of November 2026 no grid connection had been reported.[27]

    We report published targets and budgets. Cost comparisons between projects depend on scope, currency and what each figure includes, so read each number with its source.

    More in Energy and climate

    Developing in Science & Energy

    Go deeper

    Questions readers ask

    What counts as a small modular reactor?

    Generally a reactor of 300 MWe or less, designed to be built from factory-fabricated modules. Traditional reactors produce around 1,000 MWe or more per unit, and designs under about 20 MWe are sometimes called microreactors.[1][7]

    Are SMRs a new kind of technology?

    Mostly not. Most near-term SMR candidates use proven water-cooled technology, while others use fast neutron, high-temperature gas or molten salt designs.[10]

    How close is the first Western SMR?

    Canada's Darlington BWRX-300, which World Nuclear News says looks set to be the first SMR in a G7 country, has a construction licence and has applied for an operating licence. Grid connection is planned by the end of 2030.[28][2][29][25]

    What happened to NuScale's Carbon Free Power Project?

    The project, owned by Utah municipal utilities and planned for Idaho National Laboratory, raised its target power price to $89 per megawatt-hour in January 2023, which NuScale attributed to inflation in steel, equipment and other commodities. It was cancelled in November 2023, before a licence application was filed.[24][5][4]

    Why are tech companies interested in SMRs?

    Google agreed in 2024 to buy power from multiple Kairos Power reactors, up to 500 MW by 2035, and Amazon invested in X-energy to support more than 5 GW of projects.[22][23]

    What fuel do SMRs use?

    Light-water SMRs use low-enriched uranium. More than half of SMR designs in development will need HALEU, and only Russia and China currently have the infrastructure to produce it at scale.[9][30]

    Sources

    · 30 claims from 6 publishers

    Each numbered claim is a statement we checked against the sources listed with it. Tap a number in the text to see its sources in place.

    1. [1]

      Small modular reactors are generally defined as reactors of 300 MWe or less, built from factory-fabricated modules to gain economies of series production and short construction times. reportedas of 2026-10-23

    2. [2]

      In April 2025 the Canadian Nuclear Safety Commission issued Ontario Power Generation a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project. confirmedas of 2026-11-07

    3. [3]

      On 30 September 2026 the NRC issued TVA a construction permit for a BWRX-300 at Clinch River, Tennessee, completing its review in 14 months, four months ahead of schedule; TVA has not announced a construction date. reportedas of 2026-09-30

    4. [4]

      The Carbon Free Power Project was cancelled in November 2023, before UAMPS had submitted an application for a combined licence. reportedas of 2026-11-04

    5. [5]

      In January 2023 the Carbon Free Power Project's target power price was raised to $89 per megawatt-hour, which NuScale attributed to inflation and higher prices for steel, electrical equipment and other construction commodities. reportedas of 2023-01-09

    6. [6]

      TerraPower announced the official start of construction of Kemmerer Unit 1 in April 2026 and expects the project to be complete in 2030. reportedas of 2026-04-23

    7. [7]

      Traditional reactors produce around 1,000 MWe or more per unit, some SMR definitions extend to 600 MWe, and designs under about 20 MWe are sometimes called microreactors. reportedas of 2026-10-23

    8. [8]

      In SMRs, components or even entire reactor modules are designed to be built in factories and shipped to the site for assembly, potentially reducing construction times and costs. reportedas of 2026-10-23

    9. [9]

      For its 2025 funding programme, the DOE defined a Gen III+ SMR as a light-water-cooled reactor using low-enriched uranium with a single-unit net output of 50 to 350 MWe. reportedas of 2025-12-03

    10. [10]

      Most near-term SMR candidates use proven water-cooled technology; the four main options are light water, fast neutron, graphite-moderated high-temperature and molten salt reactors. reportedas of 2026-10-23

    11. [11]

      GE Vernova Hitachi's BWRX-300 is a 300 MWe water-cooled, natural-circulation SMR with passive safety systems, based on the NRC-certified ESBWR design. confirmedas of 2026-11-07

    12. [12]

      NuScale's US460 design, which received NRC standard design approval in May 2025, uses 77 MWe modules, each with core, pressurizer and steam generators inside one reactor vessel; its VOYGR plants range from 308 MWe (four modules) to 924 MWe (twelve). reportedas of 2026-11-04

    13. [13]

      The Rolls-Royce SMR is a 470 MWe design based on a small pressurised water reactor, with 90% of the SMR to be built in factory conditions. reportedas of 2025-06-10

    14. [14]

      China's ACP100 (Linglong One) is a 125 MWe integral pressurised water reactor with passive cooling for decay heat removal, which CNNC says could supply electricity, heat and desalination. reportedas of 2026-11-03

    15. [15]

      TerraPower's Natrium is a 345 MWe sodium-cooled fast reactor with molten-salt energy storage that lets the plant boost output to 500 MWe when needed. reportedas of 2026-03-05

    16. [16]

      X-energy's Xe-100 is a high-temperature gas-cooled reactor of 80 MWe per unit, planned in four-unit plants of 320 MWe. reportedas of 2026-11-06

    17. [17]

      Kairos Power's commercial KP-FHR is a 140 MWe fluoride salt-cooled reactor using 19.75% enriched TRISO fuel pebbles, operating at up to 650°C with passive shutdown and decay heat removal. reportedas of 2026-11-04

    18. [18]

      The NRC issued Kairos Power a construction permit for the 35 MWt Hermes test reactor in December 2023 and permits for the two-unit Hermes 2 facility in November 2024; Hermes 2 broke ground in April 2026. reportedas of 2026-11-04

    19. [19]

      The Department of Energy lists the advantages it sees in SMRs as small physical footprints, reduced capital investment, siting where larger plants cannot go, and incremental power additions. confirmedas of 2026-11-07

    20. [20]

      The US Department of Energy describes advanced SMRs as ranging from tens to hundreds of megawatts, for power generation, process heat, desalination or other industrial uses. confirmedas of 2026-11-07

    21. [21]

      Passive safety designs rely only on physical phenomena such as convection, gravity or resistance to high temperatures, not on engineered components working. reportedas of 2026-05-27

    22. [22]

      In October 2024 Google signed what it called the first corporate agreement to buy nuclear energy from multiple SMRs, with Kairos Power, aiming for a first reactor by 2030 and up to 500 MW by 2035. confirmedas of 2024-10-14

    23. [23]

      In October 2024 Amazon announced an investment in X-energy, including manufacturing capacity to support more than 5 GW of projects using X-energy's technology, starting with an Energy Northwest project in Washington state. confirmedas of 2024-10-16

    24. [24]

      The Carbon Free Power Project was planned as a six-module, 462 MWe NuScale plant at Idaho National Laboratory, owned by Utah Associated Municipal Power Systems (UAMPS). confirmedas of 2023-01-09

    25. [25]

      In May 2025 Ontario approved a CAD20.9 billion (USD15 billion) budget for the Darlington project and the start of construction of the first of four planned BWRX-300s, with grid connection of the first unit planned by the end of 2030. reportedas of 2026-04-02

    26. [26]

      On 5 March 2026 the NRC approved a construction permit for TerraPower's Kemmerer Unit 1 Natrium plant in Wyoming, the first for a commercial-scale non-light-water reactor in about four decades, after an 18-month review against an initial 27-month schedule. reportedas of 2026-03-05

    27. [27]

      As of the World Nuclear Association's 3 November 2026 update, the latest Linglong One milestones listed were cold functional tests in October 2025 and a steam turbine test in December 2025, with commissioning expected during 2026; no grid connection was listed. reportedas of 2026-11-03

    28. [28]

      World Nuclear News reported that the Darlington BWRX-300 looks set to be the first SMR in a G7 country. reportedas of 2026-04-02

    29. [29]

      On March 25, 2026 OPG applied for a 20-year licence to operate the first Darlington BWRX-300; the CNSC will decide after a public hearing whose date has not been announced. confirmedas of 2026-11-07

    30. [30]

      According to the World Nuclear Association, more than half of SMR designs in development will need HALEU, and only Russia and China currently have the infrastructure to produce it at scale. reportedas of 2026-10-23

    Revision history (1)
    1. Page created.

    Created Nov 7, 2026. Last reviewed by an editor on Nov 8, 2026. Next scheduled review: Feb 7, 2027.