    Hornsdale Power Reserve: the South Australian grid battery

    Also known as HPR, SA Big Battery, Hornsdale battery

    The Hornsdale Power Reserve is a grid battery near Jamestown, South Australia, built with Tesla technology, with Neoen running its commercial trading under the original agreements; its first 100 MW / 129 MWh stage was completed in November 2017 and a 50 MW / 64.5 MWh expansion followed in September 2020.[1][2][3][4] AEMO said it was the first technology other than conventional synchronous generation to provide regulation frequency services in Australia's National Electricity Market, and AEMO found that service rapid and precise.[5][6]

    Editor reviewedUpdated Wiki13 claims · 100% primaryBatteries and energy storage, Energy and climate
    Key facts

    What it is

    The Hornsdale Power Reserve (HPR) stands near Jamestown, north of Adelaide in South Australia. It shares a 275 kV grid connection point with the 300 MW Hornsdale Wind Farm next door.[1] Its services were provided under commercial agreements between the South Australian Government, Tesla, which supplied the battery technology, and Neoen, operator of the neighbouring wind farm, which ran the battery’s commercial trading.[2][3] The first 100 MW / 129 MWh stage was completed in November 2017, and a 50 MW / 64.5 MWh expansion followed in September 2020.[4]

    One of the battery’s roles goes back to the 2016 blackout. On 28 September 2016 South Australia’s power system separated from the rest of the National Electricity Market after a sudden increase in flow on the Heywood Interconnector, which links the state to Victoria, leading to the state’s black system event.[7] AEMO reported in 2018 that a System Integrity Protection Scheme, due to be fully commissioned that year, was meant to detect high flows on that interconnector and trigger the battery to discharge at 100 MW as quickly as possible. 10 MWh of the battery’s storage was set aside for the scheme.[8]

    How its capacity was split

    The Australian Energy Market Operator (AEMO) reported in 2018 that the battery was rated at 100 MW for discharging and 80 MW for charging, with 129 MWh of storage, about 75 minutes at full output.[9] Not all of it was used for trading. Under normal conditions Neoen could use 30 MW and up to 119 MWh commercially. The remaining 70 MW was reserved for power-system reliability and offered at the market price cap.[3] Battery capacity and power explained covers what these numbers mean.

    Grid services

    By early 2018 the HPR was registered for and took part in all eight frequency control ancillary services (FCAS) markets. AEMO said it was the first time any technology other than conventional synchronous generation had provided regulation FCAS in the National Electricity Market.[5] AEMO’s data showed the battery’s regulation service was both rapid and precise compared with a typical conventional generator.[6] Neoen says the battery saved South Australian consumers over 150 million dollars in its first two years of operation. That is the operator’s own figure.[10]

    The 2020 expansion and inertia

    The Australian Renewable Energy Agency (ARENA) gave 8 million Australian dollars towards the 71 million Australian dollar upgrade, led by Neoen with Tesla as partner. The project started on 19 December 2019.[11] ARENA described it as an Australian-first, large-scale demonstration of a battery providing inertia to the network, using a Tesla control mode that lets the system mimic synchronous machines. Neoen says this Virtual Machine Mode now covers the full 150 MW.[12]

    Grid batteries are now far more common. The US alone had nearly 52 GW of battery storage operating by mid-2026.[13] How grid-scale energy storage works explains the wider picture, and Battery storage fire safety covers the safety rules for such sites.

    This page describes the plant from AEMO, ARENA and operator documents. It does not cover later market reports, regulatory proceedings or ownership changes at Neoen.

    Next in the crash course

    LG Energy Solution

    LG Energy Solution is a South Korean maker of EV and grid storage batteries. Its history, US plants, shift to energy storage and 2026 results.

    More in Batteries and energy storage

    Developing in Science & Energy

    Go deeper

    Questions readers ask

    How big is the Hornsdale Power Reserve?

    The first stage was 100 MW / 129 MWh, completed in November 2017. A 50 MW / 64.5 MWh expansion was completed in September 2020.[4]

    What does the Hornsdale battery do?

    In its first period of operation it traded energy, held 70 MW in reserve for power-system reliability, took part in all eight frequency control ancillary services markets and was part of a scheme to protect the link to Victoria.[3][5][8]

    Did the battery save consumers money?

    Neoen says it saved South Australian consumers over 150 million dollars in its first two years. That figure comes from the company.[10]

    What is Virtual Machine Mode?

    A Tesla control mode that lets the battery mimic synchronous machines and provide inertia to the grid. The ARENA-funded upgrade was meant to demonstrate this at large scale, and Neoen says it now covers the full 150 MW.[12]

    Sources

    · 13 claims from 4 publishers

    Each numbered claim is a statement we checked against the sources listed with it. Tap a number in the text to see its sources in place.

    1. [1]

      The Hornsdale Power Reserve is near Jamestown, north of Adelaide in South Australia, and shares a 275 kV network connection point with the 300 MW Hornsdale Wind Farm. confirmedas of 2026-11-21

    2. [2]

      The Hornsdale Power Reserve's services were provided under commercial agreements between the South Australian Government, Tesla as battery technology provider, and Neoen, the operator of the neighbouring Hornsdale Wind Farm; AEMO was not a party to them. confirmedas of 2018-04-05

    3. [3]

      Under normal conditions 30 MW of the battery's discharge capacity, and up to 119 MWh of its energy, were available to Neoen for commercial operation, while the remaining 70 MW was reserved for power-system reliability and offered at the market price cap. confirmedas of 2018-04-05

    4. [4]

      The first 100 MW / 129 MWh stage of the Hornsdale Power Reserve was completed in November 2017, and a 50 MW / 64.5 MWh expansion was completed in September 2020. confirmedas of 2026-11-21

    5. [5]

      By early 2018 the Hornsdale Power Reserve was registered for and took part in all eight frequency control ancillary services markets, and AEMO said it was the first time regulation FCAS had been provided in the National Electricity Market by any technology other than conventional synchronous generation. confirmedas of 2018-04-05

    6. [6]

      AEMO found the battery's regulation FCAS both rapid and precise compared with the service typically provided by a conventional synchronous generator. confirmedas of 2018-04-05

    7. [7]

      AEMO notes that on 28 September 2016 the South Australian power system separated from the rest of the National Electricity Market after a sudden increase in flow on the Heywood Interconnector, leading to the black system event. confirmedas of 2018-04-05

    8. [8]

      AEMO reported in 2018 that a System Integrity Protection Scheme, then expected to be fully commissioned in the second quarter of 2018, was intended to detect high flows on the Heywood Interconnector and trigger the battery to discharge at 100 MW as quickly as possible, with 10 MWh of its storage reserved for the scheme. confirmedas of 2018-04-05

    9. [9]

      AEMO reported in 2018 that the Hornsdale Power Reserve was rated at 100 MW discharge and 80 MW charge with 129 MWh of storage, about 75 minutes at full discharge. confirmedas of 2018-04-05

    10. [10]

      Neoen says the Hornsdale Power Reserve saved South Australian consumers over 150 million dollars in its first two years of operation. reportedas of 2026-11-21

    11. [11]

      ARENA provided 8 million Australian dollars towards the 71 million Australian dollar Hornsdale Power Reserve Upgrade, led by Neoen Australia with Tesla as partner, with a project start date of 19 December 2019. confirmedas of 2026-11-21

    12. [12]

      The upgrade was meant to give an Australian-first large-scale demonstration of a battery providing inertia to the grid, using a Tesla control mode that lets the battery mimic synchronous machines; Neoen says Virtual Machine Mode now covers the full 150 MW. confirmedas of 2026-11-21

    13. [13]

      US operational battery storage capacity reached 43.6 gigawatts by the end of 2025 and nearly 52 gigawatts by mid-2026, after average annual growth of 70% over three years. confirmedas of 2026-08-07

    Revision history (1)
    1. Page created.

    Created Nov 21, 2026. Last reviewed by an editor on Nov 22, 2026. Next scheduled review: Jun 21, 2027.

    Cite this page

    "Hornsdale Power Reserve: the South Australian grid battery." ContentLora, updated Nov 21, 2026. https://contentlora.com/wiki/hornsdale-power-reserve

    Spotted an error? Suggest a correction or emailcorrections@contentlora.com.