    The PJM capacity auction explained: prices, shortfalls and bills

    PJM's capacity auction buys commitments of power plant and demand-response capacity for future delivery years, for a grid serving more than 67 million people.[1][2][3] Its auctions for 2026/2027, 2027/2028 and 2028/2029 all cleared at their price caps, and the last two fell short of PJM's reliability requirement.[4][5][6][7] PJM's market monitor attributes the tight market mainly to data centre load growth.[8]

    Editor reviewedUpdated Explainer21 claims · 100% primaryEnergy and climate, Economy and trade

    Auction prices here are dated results from PJM and its market monitor. They are not a forecast of anyone’s electric bill or investment advice.

    pjm-interconnection runs the grid and wholesale power market for more than 67 million people in all or parts of 13 states and the District of Columbia.[1] Its capacity auction has become one of the most watched numbers in US electricity, because its last three base auctions all cleared at their price caps.[4][5][6]

    How the auction works

    PJM’s main capacity auction is the Base Residual Auction, held for each future delivery year. Prices are set in dollars per megawatt-day of unforced capacity (UCAP).[6] UCAP is a resource’s maximum output adjusted for its estimated ability to perform at times of highest system risk; installed capacity (ICAP) is the total it can produce.[9]

    PJM measures the result against a one-event-in-10-years reliability standard, which for 2027/2028 meant a 20% reserve margin.[10] The auction normally runs three years ahead. After the July 2026 auction, PJM said it was working to return to that cycle.[3]

    In coordination with the governors of its 13 states and FERC, PJM set a price cap and floor, or collar, for four auctions. The 2028/2029 auction was the third under the collar.[11]

    Recent results

    Delivery yearAuctionResult
    2026/2027July 2025Cleared at the cap, 139 MW above the reliability requirement[4]
    2027/2028December 2025Cap of $333.44/MW-day; 6,623 MW short[5][12]
    2028/2029July 2026Cap of $325/MW-day; 6,831 MW short[6][7]

    Counting every auction for each delivery year, PJM’s market monitor puts the weighted average capacity price at $296.98 per MW-day for 2025/2026, $329.17 for 2026/2027 and $333.44 for 2027/2028.[13] The 2028/2029 auction bought 138,318 MW; cleared supply times the price came to $16.4 billion.[6]

    The 2027/2028 and 2028/2029 auctions were the first in PJM’s history in which the whole region fell short of its reliability requirement.[7] PJM says that does not necessarily mean it cannot serve load, but it would operate with slimmer reserves and more risk.[14]

    Gas, nuclear and coal dominate what clears. In the 2027/2028 auction cleared capacity was 43% natural gas, 21% nuclear and 20% coal, with demand response at 5% and solar at 1%.[2]

    The data centre factor

    PJM said nearly 5,100 MW of a roughly 5,250 MW rise in forecast peak load for 2027/2028 came from data centres.[15] Its independent market monitor says data centre load growth is the primary reason for recent capacity market conditions, and judged the 2025/2026, 2026/2027 and 2027/2028 results not competitive.[8]

    The monitor also put a number on it. It calculated that including existing and forecast data centre load raised capacity revenues by about $7.27 billion, or 82.1%, in the 2026/2027 auction, and by about $23.1 billion across the three auctions from 2025/2026 to 2027/2028.[16] PJM plans a reliability backstop procurement and rules that would let large new loads connect but run flexibly when needed.[17] For the wider picture, see AI data centres and power.

    What it means for power bills

    Capacity costs reach customers, but only as one part of the bill. The market monitor put capacity charges to load for the 2025/2026 delivery year at $14.9 billion.[18] PJM says capacity is a fraction of wholesale electricity costs, and wholesale costs are only part of retail bills.[19] In 2025 capacity made up 15.8% of PJM’s total wholesale cost per MWh, behind energy and transmission.[20]

    Not every customer pays the auction price, because some utilities supply themselves or use bilateral contracts.[21] The electricity prices explainer covers the other parts of a bill.

    What comes next

    PJM said the next Base Residual Auction, for the 2029/2030 delivery year, was scheduled for December 2026.[3] The price collar covers four auctions, and the 2028/2029 auction was the third.[11]

    PJM Interconnection

    PJM runs the grid and wholesale power market for 67 million people in 13 states and DC. Its history, size, capacity auctions and the data centre squeeze.

    More in Energy and climate

    Developing in Science & Energy

    Go deeper

    Questions readers ask

    What is PJM's capacity auction?

    It is the Base Residual Auction, in which PJM buys commitments from power plants and demand-response providers to be available in a future delivery year. Capacity is measured in unforced capacity (UCAP), a resource's output adjusted for how reliably it performs at times of highest system risk.[9][6][2]

    Why have PJM capacity prices been so high?

    The 2026/2027, 2027/2028 and 2028/2029 auctions all cleared at their caps. PJM's market monitor says data centre load growth is the primary reason for tight supply and high prices, and judged the 2025/2026, 2026/2027 and 2027/2028 results not competitive.[4][5][6][8]

    How much have data centres added to capacity costs?

    The market monitor calculated that including existing and forecast data centre load raised capacity market revenues by about $23.1 billion across the 2025/2026, 2026/2027 and 2027/2028 auctions.[16]

    Does the capacity price show up on my electric bill?

    Partly. PJM says capacity is a fraction of wholesale costs, which are only part of retail bills, and not all load pays the auction price. In 2025 capacity was 15.8% of PJM's total wholesale cost.[19][21][20]

    What does a shortfall mean?

    It means committed supply is below what PJM needs to meet its one-event-in-10-years reliability standard. PJM says that does not necessarily mean it cannot serve load, but it would run with slimmer reserves and more risk.[10][14]

    When is the next auction?

    PJM said the next Base Residual Auction, for the 2029/2030 delivery year, was scheduled for December 2026.[3]

    Sources

    · 21 claims from 4 publishers

    Each numbered claim is a statement we checked against the sources listed with it. Tap a number in the text to see its sources in place.

    1. [1]

      PJM Interconnection is a regional transmission organization that coordinates the movement of wholesale electricity in all or parts of 13 states and the District of Columbia, serving more than 67 million people. confirmedas of 2026-11-07

    2. [2]

      The capacity cleared in PJM's 2027/2028 auction was 43% natural gas, 21% nuclear, 20% coal, 5% demand response, 4% hydro, 2% wind, 2% oil and 1% solar. confirmedas of 2025-12-17

    3. [3]

      After the July 2026 auction PJM said the next Base Residual Auction, for the 2029/2030 delivery year, was scheduled for December 2026 as it works back toward a three-year-forward schedule. confirmedas of 2026-07-14

    4. [4]

      PJM's July 2025 auction for the 2026/2027 delivery year also cleared at the price cap, with cleared and committed capacity just 139 MW above the reliability requirement. confirmedas of 2025-12-18

    5. [5]

      PJM's 2027/2028 capacity auction, announced on 17 December 2025, cleared at the FERC-approved cap of $333.44 per MW-day across its footprint, up 1.3% from the 2026/2027 auction; cleared supply times the price totals $16.4 billion, though not all load pays that price. PJM serves more than 67 million people in 13 states and the District of Columbia. confirmedas of 2025-12-17

    6. [6]

      PJM's 2028/2029 capacity auction, announced on 14 July 2026, cleared at the FERC-approved cap of $325 per MW-day across its footprint, 2.5% below the 2027/2028 cap of $333.44, procuring 138,318 MW of capacity; cleared supply times price totals $16.4 billion. confirmedas of 2026-07-14

    7. [7]

      The 2028/2029 auction left committed capacity 6,831 MW short of PJM's reliability requirement, after a shortfall of about 6,500 MW in the previous auction; PJM said these were the first auctions in its history in which the whole region fell short. confirmedas of 2026-07-14

    8. [8]

      PJM's independent market monitor, Monitoring Analytics, said data centre load growth is the primary reason for recent capacity market conditions, including the tight supply and high prices, and found the 2025/2026, 2026/2027 and 2027/2028 capacity market results were not competitive. confirmedas of 2026-03-12

    9. [9]

      PJM's capacity auctions are run in unforced capacity (UCAP), which PJM defines as a resource's maximum output adjusted for its estimated ability to perform reliably at times of highest system risk; installed capacity (ICAP) is the total a resource can produce. confirmedas of 2025-12-17

    10. [10]

      PJM measures auction results against a one-event-in-10-years reliability standard, which for the 2027/2028 delivery year meant a 20% reserve margin. confirmedas of 2025-12-17

    11. [11]

      PJM, in coordination with the governors of its 13 states and FERC, set a price cap and floor for four capacity auctions; the 2028/2029 auction was the third held under the collar. confirmedas of 2026-07-14

    12. [12]

      PJM said the 2027/2028 auction left committed capacity 6,623 MW short of its reliability requirement, the first auction in which the whole region fell short. confirmedas of 2025-12-17

    13. [13]

      PJM's independent market monitor put the weighted average capacity price, across all auctions for each delivery year, at $296.98 per MW-day for 2025/2026, $329.17 for 2026/2027 and $333.44 for 2027/2028. confirmedas of 2026-03-12

    14. [14]

      PJM said a capacity shortfall does not necessarily mean it cannot serve load reliably, but that it would operate with slimmer reserves and more risk; it holds a 14.7% reserve margin for the 2028/2029 delivery year. confirmedas of 2026-07-14

    15. [15]

      PJM said the forecast peak load for its 2027/2028 delivery year was about 5,250 MW higher than for the previous auction and that nearly 5,100 MW of the increase was attributable to data centre demand; a PJM executive said the auction showed data centres' demand "continues to far outstrip new supply". confirmedas of 2025-12-17

    16. [16]

      The market monitor calculated that including existing and forecast data centre load raised capacity market revenues by about $7.27 billion (82.1%) in the 2026/2027 auction and by about $23.1 billion in total across the 2025/2026, 2026/2027 and 2027/2028 auctions. confirmedas of 2026-03-12· interpretation

    17. [17]

      After the 2028/2029 auction PJM said it planned a reliability backstop procurement for near-term needs and "connect and manage" rules letting large new loads such as data centres connect but operate flexibly when needed. confirmedas of 2026-07-14

    18. [18]

      The market monitor put capacity market charges to load for the 2025/2026 delivery year at $14.9 billion. confirmedas of 2026-03-12

    19. [19]

      PJM says capacity bought in its auctions is a fraction of wholesale electricity costs, alongside the daily cost of power and transmission, and that wholesale costs make up only a portion of retail bills. confirmedas of 2026-07-14

    20. [20]

      In 2025 energy (59.6%), transmission (22.4%) and capacity (15.8%) made up 97.9% of the total cost of wholesale power in PJM, which rose from $55.52 to $82.67 per MWh. confirmedas of 2025-12-31

    21. [21]

      PJM says not all load pays the auction clearing price, because of self-supply and bilateral contract arrangements. confirmedas of 2025-12-17

    Revision history (1)
    1. Page created.

    Created Nov 14, 2026. Last reviewed by an editor on Nov 15, 2026. Next scheduled review: Jan 15, 2027.

    Cite this page

    "The PJM capacity auction explained: prices, shortfalls and bills." ContentLora, updated Nov 14, 2026. https://contentlora.com/explain/pjm-capacity-auction-explained

    Spotted an error? Suggest a correction or emailcorrections@contentlora.com.