    Stargate: OpenAI's $500 billion AI data center project

    Also known as The Stargate Project

    Stargate is an AI infrastructure venture announced on 21 January 2025 that planned to invest $500 billion over four years in data centers for OpenAI in the United States, starting with $100 billion.[1] Its initial equity funders were SoftBank, OpenAI, Oracle and MGX, with SoftBank holding financial responsibility and OpenAI operational responsibility.[2] By September 2025 the partners counted nearly 7 gigawatts of planned capacity across the flagship campus in Abilene, Texas, five new US sites and CoreWeave projects.[3]

    Editor reviewedUpdated Wiki8 claims · 100% primaryArtificial intelligence, Energy and climate
    Key facts

    Stargate is a venture to build AI data centers for OpenAI in the United States, announced on 21 January 2025 with a plan to invest $500 billion over four years.[1] By September 2025 its partners called it OpenAI’s overarching AI infrastructure platform.[4]

    This page draws on the joint announcements published by SoftBank Group with OpenAI and Oracle. Investment and capacity figures are the companies’ own plans, not audited spending. We could not confirm later site or financing changes from the companies’ own releases, so the page stops at the five-site announcement.

    The January 2025 announcement

    The project was announced in Washington, D.C., as a new company intending to spend $500 billion over the next four years, beginning with $100 billion.[1] SoftBank, OpenAI, Oracle and MGX were the initial equity funders. SoftBank took financial responsibility and OpenAI took operational responsibility.[2] Arm, Microsoft, NVIDIA, Oracle and OpenAI were named as the key initial technology partners, and building began in Texas.[5]

    Abilene: the flagship campus

    The flagship campus in Abilene, Texas, runs on Oracle Cloud Infrastructure. Oracle began delivering the first NVIDIA GB200 racks in June 2025, and by September OpenAI had started early training and inference work there.[6]

    Five more sites in September 2025

    OpenAI, Oracle and SoftBank announced five new US data center sites in September 2025.[3] Three are being developed with Oracle: Shackelford County, Texas; Doña Ana County, New Mexico; and a Midwest site. They fall under an Oracle agreement for up to 4.5 gigawatts of extra capacity, which the companies said exceeds $300 billion over five years.[7] The other two, in Lordstown, Ohio, and Milam County, Texas, are developed by SoftBank and OpenAI and can scale to 1.5 gigawatts over 18 months.[8] With Abilene and projects with CoreWeave, the partners said the sites brought Stargate to nearly 7 gigawatts of planned capacity and over $400 billion of investment over three years. They set this against what they described as the $500 billion, 10-gigawatt commitment announced in January, which they said they were on track to secure by the end of 2025.[3]

    Why it matters for power and spending

    Stargate’s targets are stated in gigawatts of capacity as well as dollars.[3] The power side of AI data centers is covered in AI data centers and power and the AI data center power tracker. Whether spending of this size will pay off is argued over in the AI capex boom debate.

    OpenAI

    OpenAI is the US AI company behind ChatGPT and the GPT models. Its structure, funding, products and what changed in 2026.

    Developing in AI & Computing

    Questions readers ask

    What is Stargate?

    A company announced on 21 January 2025 that intended to invest $500 billion over four years building AI infrastructure for OpenAI in the United States, beginning with $100 billion. By September 2025 the partners described it as OpenAI's overarching AI infrastructure platform.[1][4]

    Who owns and runs Stargate?

    The initial equity funders were SoftBank, OpenAI, Oracle and MGX. SoftBank and OpenAI are the lead partners, with SoftBank holding financial responsibility and OpenAI operational responsibility.[2]

    Where are the Stargate data centers?

    The flagship campus is in Abilene, Texas. Five more US sites were announced in September 2025, in Shackelford County and Milam County in Texas, Doña Ana County in New Mexico, Lordstown in Ohio, and a Midwest location.[6][7][8]

    How big is Stargate?

    In September 2025 the partners said Stargate had nearly 7 gigawatts of planned capacity and over $400 billion of investment over three years, against a commitment of $500 billion and 10 gigawatts.[3]

    Is Stargate running yet?

    The Abilene campus was running on Oracle Cloud Infrastructure by September 2025. Oracle began delivering NVIDIA GB200 racks there in June 2025, and OpenAI had started early training and inference work.[6]

    Sources

    · 8 claims from 1 publisher

    Each numbered claim is a statement we checked against the sources listed with it. Tap a number in the text to see its sources in place.

    1. [1]

      Stargate was announced in Washington on 21 January 2025 as a new company intending to invest $500 billion over four years in AI infrastructure for OpenAI in the United States, starting with $100 billion. confirmedas of 2025-01-22

    2. [2]

      Stargate's initial equity funders were SoftBank, OpenAI, Oracle and MGX, with SoftBank holding financial responsibility and OpenAI operational responsibility. confirmedas of 2025-01-22

    3. [3]

      On 23 September 2025 OpenAI, Oracle and SoftBank announced five new US data center sites, which with the Abilene, Texas, flagship and CoreWeave projects brought Stargate to nearly 7 gigawatts of planned capacity and over $400 billion of investment over three years; the companies said this put them on a clear path to securing the full $500 billion, 10-gigawatt commitment by the end of 2025. confirmedas of 2025-09-24

    4. [4]

      By September 2025 the partners described Stargate as OpenAI's overarching AI infrastructure platform. confirmedas of 2025-09-24

    5. [5]

      Arm, Microsoft, NVIDIA, Oracle and OpenAI were named as Stargate's key initial technology partners, and the buildout began in Texas. confirmedas of 2025-01-22

    6. [6]

      The flagship Stargate campus in Abilene, Texas, runs on Oracle Cloud Infrastructure; Oracle began delivering the first NVIDIA GB200 racks there in June 2025, and OpenAI had started early training and inference work on it by September 2025. confirmedas of 2025-09-24

    7. [7]

      Three of the new sites, in Shackelford County, Texas, Doña Ana County, New Mexico, and an unnamed Midwest location, are developed with Oracle under an agreement for up to 4.5 gigawatts of additional capacity that the companies said exceeds $300 billion over five years. confirmedas of 2025-09-24

    8. [8]

      The other two sites, in Lordstown, Ohio, and Milam County, Texas, are developed by SoftBank and OpenAI and can scale to 1.5 gigawatts over 18 months. confirmedas of 2025-09-24

    Revision history (1)
    1. Page created.

    Created Nov 14, 2026. Last reviewed by an editor on Nov 15, 2026. Next scheduled review: Nov 14, 2027.

    Cite this page

    "Stargate: OpenAI's $500 billion AI data center project." ContentLora, updated Nov 14, 2026. https://contentlora.com/wiki/stargate-project

    Spotted an error? Suggest a correction or emailcorrections@contentlora.com.