How data centres connect to the grid: the large-load rules
"Large loads" are very large electricity users, such as data centres, that connect to the high-voltage transmission system.[1][2] On 23 October 2025 the Secretary of Energy proposed that FERC standardise how they connect, including when they share a connection with a power plant.[2] In June 2026 FERC issued six show cause orders telling grid operators their large-load rules appeared inadequate, and later extended their deadline to respond to mid-November.[3][4] In October 2026 it largely rejected PJM's plan.[5] States are also writing their own large-load tariffs and rules.[6][7]
A “large load” is a very large electricity customer, such as a data centre, that connects to the high-voltage interstate transmission system.[1] In October 2025 DOE asked FERC to standardise how such loads connect.[2] This page explains the federal proposal, what FERC did with it in 2026, and how states and grid operators are writing their own rules. For why demand is rising, see AI data centers and power.
This page describes rules and proposals as of 14 November 2026. FERC’s own website blocks automated access, so FERC actions are cited from the Federal Register and from trade press that attributes them to FERC.
Why the rules are under pressure
NERC’s long-term reliability assessment, published in January 2026, expects summer peak demand to rise 24% over ten years, with data centres accounting for most of the increase.[8] In Texas, Governor Greg Abbott said in August 2026 that interconnection requests in ERCOT totalled about 474 GW, more than five times its record peak, and that about 90% were data centres.[9] ERCOT said it aimed to audit hundreds of data centre proposals by 10 December before large-load connections resume.[10]
Reliability is a second concern. About 3,800 MW of data centre load tripped offline in northern Virginia on 22 July 2026 after a fault on a 230-kV line, the largest such event in PJM’s history, according to the grid operator.[11]
DOE’s October 2025 proposal
On 23 October 2025 the Secretary of Energy proposed an advance notice of proposed rulemaking for FERC, docket RM26-4. As proposed, the reforms would standardise interconnection procedures and agreements for large loads, including loads seeking to share a point of interconnection with new or existing power plants.[2] Utility Dive reported that the proposal drew more than 3,500 pages of comments.[1]
FERC’s June 2026 show cause orders
FERC listed the large-load docket as the first electric item for its 18 June 2026 open meeting.[12] That day it issued six show cause orders finding that grid operators’ large-load interconnection rules appeared inadequate.[3] Utility Dive reported the five issues FERC wants addressed: transmission service and study processes, preventing cost shifts, co-location and behind-the-meter generation, new services for flexible large loads, and studies for generators serving nearby large loads.[13]
FERC later extended the grid operators’ deadline to respond until mid-November 2026.[4] Utility Dive reported that FERC said states will continue to regulate the terms of retail sales to large loads, which entities may make those sales, and siting and construction decisions.[14]
The PJM decision
In October 2026, Utility Dive reported, FERC largely rejected PJM’s plan for connecting data centres and other large loads. That included an interim service that would have let large loads connect without matching new capacity if they agreed to be curtailed ahead of grid emergencies; FERC found parts of the plan intruded on state jurisdiction over retail rates and appeared to discriminate against large loads. FERC approved PJM’s definition of large loads and its plan for a large-load registry.[5]
State rules
The Smart Electric Power Alliance counted 77 large-load tariffs pending or in place across 36 states as of March 2026; state regulators approved 29 in 2025, against 14 from 2018 to 2024.[6] On 9 July 2026 the Public Utility Commission of Texas approved rules requiring large computational loads in ERCOT to stay connected through grid disturbances; ERCOT said it had seen 28 trips of at least 100 MW since 2023.[7] For the latest data centre power developments, see the AI data center power tracker.
Read next
AI data center power tracker: 2026 deals, grid rules and pauses
A dated record of 2026 AI data center power news to 14 November: nuclear and gas deals, FERC and NERC action, grid trips, and pauses in Texas and New York.
Developing in Science & Energy
Questions readers ask
What is a large load?
It is a very large electricity customer, such as a data centre, connecting to the interstate transmission system. DOE's October 2025 proposal covered such loads, including ones that share a point of interconnection with new or existing power plants.[2]
What did DOE ask FERC to do?
On 23 October 2025 the Secretary of Energy proposed an advance notice of proposed rulemaking that would standardise interconnection procedures and agreements for large loads (FERC docket RM26-4). Utility Dive reported that the proposal drew more than 3,500 pages of comments.[2][1]
What did FERC decide in June 2026?
At its 18 June 2026 meeting FERC took up the large-load docket and issued six show cause orders finding grid operators' large-load rules appeared inadequate. Utility Dive reported that it asked them to address five issues, including cost shifts, co-location and services for flexible loads.[12][3][13]
What happened to PJM's large-load plan?
Utility Dive reported that FERC in October 2026 largely rejected PJM's plan, including interim service that would have let large loads connect without matching new capacity if they agreed to be curtailed, finding parts intruded on state jurisdiction and appeared to discriminate against large loads. FERC approved PJM's large-load definition and registry.[5]
Do states still have a say?
Yes. Utility Dive reported FERC saying states will continue to regulate retail sales to large loads and siting decisions. The Smart Electric Power Alliance counted 77 large-load tariffs pending or in place across 36 states as of March 2026.[14][6]
Why do grid operators worry about data centres dropping offline?
About 3,800 MW of data centre load tripped offline in northern Virginia on 22 July 2026, the largest such event in PJM's history. Texas regulators approved rules in July 2026 requiring large computational loads in ERCOT to stay connected through grid disturbances.[11][7]
Sources
· 14 claims from 2 publishers
Each numbered claim is a statement we checked against the sources listed with it. Tap a number in the text to see its sources in place.
- [1]
The US Department of Energy directed FERC in October 2025 to set rules for connecting data centres to the transmission system, and the proposal drew more than 3,500 pages of comments. reportedas of 2026-06-22
- 6 takeaways from FERC's data center interconnection decision · Utility Dive · Secondary source · 2026-06-22 · Body (retrieved 2026-11-07)
- 6 takeaways from FERC's data center interconnection decision · Utility Dive · Secondary source · 2026-06-22 · Body (retrieved 2026-11-07)
- [2]
On 23 October 2025 the Secretary of Energy proposed that FERC adopt rules to standardise interconnection procedures and agreements for large loads connecting to the transmission system, including loads sharing a connection point with new or existing power plants (FERC docket RM26-4). confirmedas of 2026-08-14
- Federal Energy Regulatory Commission: Regulatory Agenda · Federal Register (Federal Energy Regulatory Commission) · Primary source · 2026-08-14 · Item 472: Interconnection of Large Loads to the Interstate Transmission System (retrieved 2026-11-14)
- Federal Energy Regulatory Commission: Regulatory Agenda · Federal Register (Federal Energy Regulatory Commission) · Primary source · 2026-08-14 · Item 472: Interconnection of Large Loads to the Interstate Transmission System (retrieved 2026-11-14)
- [3]
Utility Dive reported that on June 18, 2026 FERC issued six show cause orders finding grid operators' large-load interconnection rules appeared inadequate, naming five issues including cost shifts, co-location and services for flexible loads. reportedas of 2026-06-22
- 6 takeaways from FERC's data center interconnection decision · Utility Dive · Secondary source · 2026-06-22 · First paragraph (retrieved 2026-11-07)
- 6 takeaways from FERC's data center interconnection decision · Utility Dive · Secondary source · 2026-06-22 · Body (retrieved 2026-11-07)
- [4]
Utility Dive reported in August 2026 that FERC had extended grid operators' deadline to respond to the show cause orders until mid-November. reportedas of 2026-08-24
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: Microsoft, PowerHouse Hillwood dispute data center service agreements (Aug. 24, 2026) (retrieved 2026-11-07)
- [5]
Utility Dive reported that FERC in October 2026 largely rejected PJM's plan for connecting data centers and other large loads, including its Interim Resource Adequacy Service, which would have let large loads connect without matching new capacity if they agreed to be curtailed ahead of grid emergencies, finding that key parts intruded on state jurisdiction over retail rates and appeared to discriminate against large loads; FERC approved PJM's large-load definition and registry. reportedas of 2026-10-12
- FERC rejects most of PJM's large load interconnection plan · Utility Dive · Secondary source · 2026-10-12 · Opening paragraph (retrieved 2026-11-14)
- FERC rejects most of PJM's large load interconnection plan · Utility Dive · Secondary source · 2026-10-12 · Second paragraph (retrieved 2026-11-14)
- FERC rejects most of PJM's large load interconnection plan · Utility Dive · Secondary source · 2026-10-12 · Second paragraph (retrieved 2026-11-14)
- FERC rejects most of PJM's large load interconnection plan · Utility Dive · Secondary source · 2026-10-12 · Body (retrieved 2026-11-14)
- [6]
The Smart Electric Power Alliance counted 77 large-load tariffs pending or in place across 36 US states as of March 2026; state regulators approved 29 in 2025, against 14 from 2018 to 2024. reportedas of 2026-03-31
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: Large load tariffs proliferate (March 31, 2026) (retrieved 2026-11-07)
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: Large load tariffs proliferate (March 31, 2026) (retrieved 2026-11-07)
- [7]
On July 9, 2026 the Public Utility Commission of Texas unanimously approved rules requiring large computational loads in ERCOT to stay connected through grid disturbances; ERCOT said it had seen 28 trips of at least 100 MW since 2023. reportedas of 2026-07-13
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: Texas PUC approves ride-through rules for data centers (July 13, 2026) (retrieved 2026-11-07)
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: Texas PUC approves ride-through rules for data centers (July 13, 2026) (retrieved 2026-11-07)
- [8]
NERC's Long-Term Reliability Assessment, published in January 2026, expects summer peak demand to rise 24% over ten years, with data centres accounting for most of the increase. reportedas of 2026-05-05· forecast
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: NERC issues Level 3 alert (May 5, 2026) (retrieved 2026-11-07)
- [9]
On August 3, 2026 Texas Governor Greg Abbott called for an audit of all data centres in ERCOT's interconnection queue, pausing new connections; he said queue requests totalled about 474 GW, more than five times ERCOT's record peak, and about 90% were data centres. reportedas of 2026-08-05
- Texas hits pause on data center interconnections · Utility Dive · Secondary source · 2026-08-05 · Dive Brief (retrieved 2026-11-07)
- Texas hits pause on data center interconnections · Utility Dive · Secondary source · 2026-08-05 · Dive Brief (retrieved 2026-11-07)
- [10]
ERCOT said in August 2026 that it aimed to audit hundreds of data centre proposals by December 10, a step needed before large-load connections can resume; about 300 data centres of 75 MW or more are in its Batch Zero study process. reportedas of 2026-08-21
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: ERCOT aims to complete Texas governor's data center audit by December (Aug. 21, 2026) (retrieved 2026-11-07)
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: ERCOT aims to complete Texas governor's data center audit by December (Aug. 21, 2026) (retrieved 2026-11-07)
- [11]
About 3,800 MW of data centre load tripped offline in northern Virginia on July 22, 2026 after a fault on a 230-kV line, the largest such event in PJM's history, according to the grid operator. reportedas of 2026-08-12
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: PJM eyes data center, crypto reliability requirements (Aug. 12, 2026) (retrieved 2026-11-07)
- [12]
FERC listed the large-load interconnection docket (RM26-4) as the first electric item for its 18 June 2026 open meeting. confirmedas of 2026-06-16
- Federal Energy Regulatory Commission: Sunshine Act Meeting Notice (June 18, 2026) · Federal Register (Federal Energy Regulatory Commission) · Primary source · 2026-06-16 · Meeting details (retrieved 2026-11-14)
- Federal Energy Regulatory Commission: Sunshine Act Meeting Notice (June 18, 2026) · Federal Register (Federal Energy Regulatory Commission) · Primary source · 2026-06-16 · Item E-1: Interconnection of Large Loads to the Interstate Transmission System (retrieved 2026-11-14)
- [13]
Utility Dive reported that FERC's June 2026 show cause orders asked grid operators to address five issues in their large-load rules - transmission service and study processes, preventing cost shifts, co-location and behind-the-meter generation, new services for flexible large loads, and studies for generators serving nearby large loads. reportedas of 2026-06-22
- 6 takeaways from FERC's data center interconnection decision · Utility Dive · Secondary source · 2026-06-22 · Body, list of five issues (retrieved 2026-11-07)
- 6 takeaways from FERC's data center interconnection decision · Utility Dive · Secondary source · 2026-06-22 · Body, list of five issues (retrieved 2026-11-07)
- [14]
In its PJM order, FERC said states will continue to regulate the terms of retail sales to large loads, which entities may make retail sales, and siting and construction decisions for large-load projects, according to Utility Dive. reportedas of 2026-06-22
- 6 takeaways from FERC's data center interconnection decision · Utility Dive · Secondary source · 2026-06-22 · Section "FERC stays in its lane" (retrieved 2026-11-07)
- 6 takeaways from FERC's data center interconnection decision · Utility Dive · Secondary source · 2026-06-22 · Section "FERC stays in its lane" (retrieved 2026-11-07)
Revision history (1)
- Page created.
Created Nov 14, 2026. Last reviewed by an editor on Nov 15, 2026. Next scheduled review: Feb 14, 2027.
Cite this page
"How data centres connect to the grid: the large-load rules." ContentLora, updated Nov 14, 2026. https://contentlora.com/explain/large-load-interconnection-explained
Spotted an error? Suggest a correction or emailcorrections@contentlora.com.