    US exports of liquefied natural gas (LNG) are rising fast as new terminals come online. EIA puts them at 15.1 billion cubic feet per day (Bcf/d) in 2025 and forecasts 17.6 Bcf/d in 2026 and 19.0 Bcf/d in 2027.[1] Plaquemines LNG shipped its first cargo in December 2024, Corpus Christi Stage 3 was completed in August 2026, and Golden Pass shipped its first cargo in April 2026.[2][3][4]

    Editor reviewedUpdated Explainer20 claims · 100% primaryEnergy and climate
    Reading level: 1 passage differs; the rest is the same for everyone.

    Export figures and forecasts here come from the US Energy Information Administration (EIA) and are dated snapshots. They are not investment advice or a price forecast.

    The United States is in the middle of a second wave of LNG export growth. EIA forecasts exports of 17.6 billion cubic feet per day (Bcf/d) in 2026 and 19.0 Bcf/d in 2027, up from 15.1 Bcf/d in 2025, as new export capacity ramps up.[1] EIA points to three projects adding new capacity: Plaquemines LNG, Corpus Christi Stage 3 and Golden Pass LNG.[5]

    How big US LNG exports have become

    US baseload export capacity grew from about 1 Bcf/d in 2016 to about 11.44 Bcf/d at the end of 2023, according to EIA.[6] In 2025 exports rose 26% to 15.1 Bcf/d, a larger increase than from any other country, and the US share of global LNG exports rose from 21% to 26%.[7] Global LNG trade reached a record 56.3 Bcf/d that year, driven largely by expanding US capacity.[8]

    Growth continued in 2026. Exports averaged 17.4 Bcf/d in the first half, 23% more than a year earlier and the fastest growth since large-scale US exports began in 2016.[9] For how gas is liquefied and shipped, see natural gas and LNG explained.

    Capacity figures come in two kinds. Nominal capacity is what a terminal produces in a year under normal conditions; peak capacity is output under optimal conditions. Terminals often run above nominal but below peak.[10]

    The new terminals

    TerminalMilestoneCapacity (EIA)
    Plaquemines LNG, LouisianaFirst cargo 26 December 2024[2]2.6 Bcf/d nominal when both phases are complete[2]
    Corpus Christi Stage 3, TexasProduction from December 2024; completed 28 August 2026[3]Terminal total 3.1 Bcf/d nominal[3]
    Golden Pass LNG, TexasFirst cargo 22 April 2026[4]2.0 Bcf/d nominal across three trains[11]

    Plaquemines LNG was the eighth US export terminal. Its developer, Venture Global LNG, is building it in two phases.[2] It used mid-scale liquefaction, which builds faster, and shipped its first cargo about 30 months after the investment decision.[12] By mid-2026 EIA said it was exporting at full capacity.[9]

    Corpus Christi Stage 3 is an expansion of Cheniere’s existing Texas terminal. With its seventh and last train complete, Corpus Christi became the second-largest US LNG facility, behind Sabine Pass at 3.6 Bcf/d.[3] A further two-train midscale project, adding 0.4 Bcf/d, is expected online in 2028.[13]

    Golden Pass LNG, the ninth US terminal, is owned 70% by QatarEnergy and 30% by ExxonMobil. It reached its investment decision in February 2019 but was delayed after its lead contractor filed for bankruptcy in 2024.[14] Its first cargo left on 22 April 2026, and EIA said it was the only new US terminal expected to begin shipments in 2026.[4] In November 2026 EIA said Train 1 exports had been slower than expected for months, but that Golden Pass had since reported a sustained rise in feedgas demand.[15]

    The Hormuz shock

    The new capacity arrived as global supply tightened. EIA says the closure of the Strait of Hormuz since 28 February 2026 cut off about 20% of global LNG supplies, and that Qatari exports have fallen as a result.[16] Before the disruption, EIA estimated that around a fifth of global LNG trade passed through the strait.[17]

    Prices abroad rose sharply. Citing Bloomberg data, EIA said Europe’s TTF near-month futures price climbed from an average of $11.27 per MMBtu in February 2026 to $28.51 in October, and Asia’s Japan-Korea Marker from $10.82 to $28.59.[18] With US prices falling at the same time, EIA said US terminals were running near full capacity.[19] The Strait of Hormuz crisis page covers the disruption itself.

    Europe as a buyer

    European countries raised LNG imports by 29% in 2025, more than any other region.[8] The EU is also banning Russian LNG, with all imports to end by 31 December 2026; see the EU’s ban on Russian gas imports.[20]

    What to watch

    Golden Pass aimed to start Train 2 in the second half of 2026 and Train 3 in the first half of 2027.[11] EIA’s forecast of 19.0 Bcf/d for 2027 rests on new capacity ramping up as planned.[1]

    More in Energy and climate

    Developing in Science & Energy

    Go deeper

    Questions readers ask

    How much LNG does the US export?

    EIA puts US LNG exports at 15.1 Bcf/d in 2025, up 26% on 2024, and forecasts 17.6 Bcf/d in 2026 and 19.0 Bcf/d in 2027. The US supplied 26% of global LNG exports in 2025.[1][7]

    Which new terminals are driving the increase?

    Plaquemines LNG in Louisiana, Corpus Christi Stage 3 in Texas and Golden Pass LNG in Texas. EIA says Plaquemines and Corpus Christi Stage 3 add 4.0 Bcf/d of nominal capacity when complete, and Golden Pass Train 1 adds 0.7 Bcf/d.[5]

    Who owns Golden Pass LNG?

    A joint venture of QatarEnergy (70%) and ExxonMobil (30%). It shipped its first cargo on 22 April 2026, after delays caused by its lead contractor's 2024 bankruptcy filing.[14][4]

    What does the Strait of Hormuz have to do with US LNG?

    EIA says the strait's closure since 28 February 2026 cut off about 20% of global LNG supply and cut Qatari exports. International gas prices rose to their highest since December 2022, and US terminals ran near full capacity.[16][19]

    What is the difference between nominal and peak capacity?

    Nominal capacity is what a terminal produces in a year under normal conditions; peak capacity is output under optimal conditions. Terminals often run above nominal but below peak.[10]

    What new capacity is still to come?

    Golden Pass planned to start Train 2 in the second half of 2026 and Train 3 in the first half of 2027. A Corpus Christi midscale expansion adding 0.4 Bcf/d is expected online in 2028.[11][13]

    Sources

    · 20 claims from 4 publishers

    Each numbered claim is a statement we checked against the sources listed with it. Tap a number in the text to see its sources in place.

    1. [1]

      EIA's November 2026 Short-Term Energy Outlook puts US LNG exports at 15.1 billion cubic feet per day (Bcf/d) in 2025 and forecasts 17.6 Bcf/d in 2026 and 19.0 Bcf/d in 2027, as new export capacity ramps up. confirmedas of 2026-11-10· forecast

    2. [2]

      Plaquemines LNG in Louisiana, the eighth US LNG export terminal, shipped its first cargo on 26 December 2024; developed by Venture Global LNG in two phases, it will have a total nominal capacity of 2.6 Bcf/d when both are complete. confirmedas of 2025-01-13

    3. [3]

      Cheniere completed Corpus Christi Liquefaction Stage 3 in Texas on 28 August 2026, taking control of the last of its seven trains; Stage 3 began producing LNG in December 2024 and raised the Corpus Christi terminal's nominal capacity to 3.1 Bcf/d, second in the US after Sabine Pass at 3.6 Bcf/d. confirmedas of 2026-09-15

    4. [4]

      Golden Pass LNG in Texas, the ninth US LNG terminal, shipped its first cargo from Train 1 on 22 April 2026, 23 days after first LNG production in March; EIA said it was the only new US terminal expected to begin shipments in 2026. confirmedas of 2026-04-23

    5. [5]

      EIA says Plaquemines LNG and Corpus Christi Stage 3 together add 4.0 Bcf/d of nominal US export capacity when complete, and Golden Pass Train 1 adds another 0.7 Bcf/d. confirmedas of 2026-09-01

    6. [6]

      EIA says US LNG baseload export capacity grew from about 1 billion cubic feet per day (Bcf/d) in 2016 to about 11.44 Bcf/d at the end of 2023, with peak capacity of about 14.01 Bcf/d, and that 9.69 Bcf/d more was under construction at the end of 2023. confirmedas of 2023-12-31

    7. [7]

      EIA says US LNG exports rose 26% to 15.1 Bcf/d in 2025, a larger increase than from any other country, and that the US share of global LNG exports rose from 21% in 2024 to 26% in 2025. confirmedas of 2026-07-14

    8. [8]

      Global LNG trade rose 5.4% to a record 56.3 Bcf/d in 2025, driven largely by expanding US export capacity, according to EIA's reading of GIIGNL data; European LNG imports rose 29% that year. confirmedas of 2026-07-14

    9. [9]

      US LNG exports averaged 17.4 Bcf/d in the first half of 2026, 23% more than a year earlier, the fastest growth since large-scale US exports began in 2016; EIA said Plaquemines LNG was exporting at full capacity. confirmedas of 2026-09-01

    10. [10]

      EIA defines nominal capacity as the LNG a terminal produces in a year under normal operating conditions and peak capacity as output under optimal conditions; terminals often run above nominal but below peak capacity. confirmedas of 2025-01-13

    11. [11]

      Golden Pass has three trains of about 0.7 Bcf/d nominal capacity each, for 2.0 Bcf/d in total; in April 2026 the developer aimed to start Train 2 in the second half of 2026 and Train 3 in the first half of 2027. confirmedas of 2026-04-23· forecast

    12. [12]

      EIA says Plaquemines LNG started production and shipped its first Phase 1 cargo about 30 months after Venture Global's final investment decision, using mid-scale liquefaction technology that has a shorter construction timeline. confirmedas of 2025-01-13

    13. [13]

      A further Corpus Christi Liquefaction Midscale project, with two trains adding 0.4 Bcf/d of nominal capacity, is under construction and expected online in 2028, according to EIA. confirmedas of 2026-09-15· forecast

    14. [14]

      Golden Pass LNG is a joint venture of QatarEnergy (70%) and ExxonMobil (30%); it reached a final investment decision in February 2019 but was delayed after its lead construction contractor filed for Chapter 11 bankruptcy in 2024. confirmedas of 2026-04-23

    15. [15]

      In November 2026 EIA said Golden Pass had reported a sustained rise in feedgas demand in recent weeks after months of slower-than-expected exports from Train 1 since its April startup. confirmedas of 2026-11-10

    16. [16]

      EIA says the closure of the Strait of Hormuz since 28 February 2026 cut off about 20% of global LNG supplies and caused Qatari exports to fall in 2026, and that Asian buyers are competing with European buyers for spot cargoes. confirmedas of 2026-07-14

    17. [17]

      EIA estimated that flows through Hormuz in 2024 and early 2025 made up more than a quarter of global seaborne oil trade and about a fifth of world oil consumption, and that around a fifth of global LNG trade passed through it in 2024, mainly from Qatar. confirmedas of 2025-06-16

    18. [18]

      EIA, citing Bloomberg data, said the European TTF near-month futures price rose from an average of $11.27 per MMBtu in February 2026 to $28.51 in October, and the Japan-Korea Marker from $10.82 to $28.59, since the US-Iran conflict began on 28 February. confirmedas of 2026-11-10

    19. [19]

      In November 2026 EIA said international natural gas prices had climbed to their highest since December 2022 while US Henry Hub prices fell, with US LNG export terminals running near full capacity. confirmedas of 2026-11-10

    20. [20]

      Under the agreed regulation, Russian LNG imports are phased out by 31 December 2026 and pipeline gas by 30 September 2027; a member state whose gas storage is below the required filling level may extend the pipeline deadline to 31 October 2027. confirmedas of 2025-12-17

    Revision history (1)
    1. Page created.

    Created Nov 14, 2026. Last reviewed by an editor on Nov 15, 2026. Next scheduled review: May 14, 2027.

    Cite this page

    "The 2026 US LNG export wave: new terminals and record exports." ContentLora, updated Nov 14, 2026. https://contentlora.com/explain/us-lng-export-wave-2026

    Spotted an error? Suggest a correction or emailcorrections@contentlora.com.